Using the Requirements Creation Process to Improve Project Estimates

Estimation can be one of the most difficult parts of a project. Important questions must be asked in order to form the right figures and plans. How long will the project take? How many resources will it consume? Consultants may also ask the following question: What is the appropriate amount to bid on this project? These questions are not easy to answer at the outset when one generally has only a vague idea of what will be required throughout the project.

The good news is that there is a fairly simple way to improve project estimation and, consequently, the bidding process. Most people do not realize that the requirements creation process can lend insight into the length and scope of a project. Let me give you an example of how this method works and then explain how you can implement it within your own company.

The Story

Back in 1992, I was working for a consulting company named The Kernel Group (TKG). During this time, I was put in charge of porting Tivoli's software from Sun's Solaris operating system to IBM's AIX operating system. The project was to be done under a fixed bid, and consequently, we at TKG knew that estimating the effort required to port the code was of paramount importance.

I looked at the code with a coworker of mine, and he came to the conclusion that if Tivoli didn't make the project hard for us in some unspecified way, we could port the million or so lines of code in about a weekend. I told him that he was nuts - that it would take at least a week, maybe even two. We jointly decided that we probably ought to call it three weeks just to be safe. We also decided, rather smugly, not to report our padding of the schedule to evil upper management.

As a result, evil upper management drastically expanded the project bid to $325,000, and my coworker and I thought that this was a ridiculously high price. We believed that we were gouging the customer and that they would never accept it.

Yet they did accept it, and once the project began, we proceeded to discover how truly terrible we as software engineers were at the task of project estimation. To make a long story short, the porting schedule expanded to exceed our original estimate and we consumed not only all of the $325,000, but a whole lot more on top of it.

The Formula

Now our consulting company was religious about tracking employee time on a per-project basis, and so we broke every project into phases: requirements/specification, design, coding, testing, debugging, documentation, training, etc. This project was no different in that respect; we broke it down into its respective phases as well.

Just before we started working on the project in question, I read a book called Practical Software Metrics for Project Management and Process Improvement by Robert B. Grady. (By the way, this is a truly fabulous book that I would highly recommend to anyone who is managing software development projects.) According to the book, one of Grady's rules of thumb is that 6-8% of every software project is usually eaten up in the requirements/specification phase.

One of the conclusions that Grady comes to in his work is that you can use this fact to estimate total project size. In other words, if it took 60 hours to do the specification, that's probably 6% of the job and the job will be 1000 hours. Following such logic, a six hour specification implies a 100 hour job. Since the specification always comes first in any project, you can get some pretty reliable estimates from this method alone. In fact, in my experience as both a programmer and the CEO of a software company, I have found it to be incredibly accurate and useful.

A second way to triangulate this project estimate is to ask experts in the area for their opinions - hopefully they will be better at project estimation than my coworker and I were that first time. A third way is to select an appropriate metric for estimation. For example, one could use line of code counts or function points in estimating the length and scope of software projects. For architecture projects, you might use number of pages in the drawings or square feet planned as similar analogies. Every project has some gross measure of its size that is available at the outset and can be used to plan the overall project in addition to this method I've described of tracking time against the earliest phases.

So back to the story. We really blew it on estimating and bidding on that first project for Tivoli, but when the next one came around, we had data on the portion of the overall project that the requirements phase had taken up. This allowed us to use Grady's ratio to predict overall project size, and we found that on this second project, we came up with a very accurate project estimate. This worked very well for all of the subsequent fixed-cost consulting work we did for Tivoli.

Partially due to the strength of the solution and how well it ran on IBM's AIX operating system, Tivoli was able to eventually sell their company to IBM for 743 million dollars in 1995.

For a consultancy that is doing fixed-cost projects, this concept of using the standard ratio of requirements phase to overall project length is a very powerful project estimation technique. It can eliminate erroneous bidding and its resulting costs, which is a major concern for such companies.

Accurate Bidding

Overbidding on a consulting job means that you won't get the work in the first place, because the potential customer will give it to your competitor at a cheaper price. Underbidding, however, means you will win the deal and lose money. Neither situation is acceptable for businesses today, and yet, most consultancies do a poor job in this area. One way to make more precise bids is to use a key performance indicator, which is a tool used to measure progress towards a strategic business goal. For example, the number you want to minimize in this situation is defined by the formula [(E-A)/E], where:

E = estimated hours to complete the project
A = actual hours spent to complete the project

It is important to keep this KPI value as close to zero as possible, which indicates that you are bidding on projects more accurately.

Just tracking this number is a great first step towards better bidding, and you can get the necessary data to calculate it from any timesheet system, including a paper one. Automated timesheet systems, however, are generally even more effective in this area because they often have reports to calculate the KPI figure for you.

Improving adherence to your estimate can be difficult for some companies until they understand the ratio concept described above. An example of this is illustrated in the following diagram, which shows how the formula can work for any business. Your company's magic number may not be 6-8% like Grady's, but once you determine your own ratio for specification to total project length, you can use it again and again.

usingtherequirements1

Making it Work

I currently run a software company, Journyx, and I can assure you that this project estimation technique continues to be successfully employed by many of our customers to their great advantage. It is easy to implement and you can do it too. Once you do, you will start producing laser sharp estimates before you know it. And that's a result we can all feel good about requiring.

Happy estimating!

Don't forget to leave your comments below


Curt Finch is the CEO of Journyx. Journyx offers customers two solutions to reach the highest levels of profitability: Journyx Timesheet - a timesheet and expense management solution for the entire enterprise - and Journyx ProjectXecute - a solution that unites project and process planning with resource management. Journyx has thousands of customers worldwide and is the first and only company to establish Per Person/Per Project Profitability (P5), a proprietary process that enables customers to gather and analyze information to discover profit opportunities. Curt is an avid speaker and author, and recently published "All Your Money Won't Another Minute Buy: Valuing Time as a Business Resource." Curt authors a project management blog and you can follow him on Twitter.

Comments (7)Add Comment
ckovacic
...
written by Casey Kovacic, September 01, 2009
Thanks for the article. Now I have another question--how do you accurately estimate the requirements/spec phase? That's what I am being asked to do. One problem with this is that we start projects at differing levels of scope knowledge. I'd appreciate your thoughts on this.

Thank you.
Kupe
...
written by Kupe Kupersmith, September 01, 2009
@ckovacic - You hit on one of the many items you need to consider when estimating the time for the requirments phase. If you have 21 minutes check out this webcast to give some insight on other things to consider. https://www2.gotomeeting.com/register/352622386

I'd love to hear your feedback.

-Kupe
clf99
...
written by Curt Finch, September 02, 2009
Estimating the Req/Spec phase. I'd try something like 'How many square feet is it?' or 'How many GUI screens will it have?' or something that provides a base measure of the relative size of the project. There's got to be something.
judo
...
written by Tony Iosifidis, September 02, 2009
Very good article. I have found that specifications and/or requirements can vary from one project to the next. What level of detail is customary when using the 6% rule?
clf99
...
written by Curt Finch, September 02, 2009
Judo, I don't understand your question exactly. The idea is that measure the number of hours your projects typically take in the requirements phase as a percentage of total project time, measured in hours. This requires the use of phase based or task based project time tracking. That's the hard part, because everyone hates timesheets.

-Curt Finch - http://timesheet.journyx.com/
judo
...
written by Tony Iosifidis, September 08, 2009
Curt,
What I had in mind is that the time it takes to create requirements/specifications is directly related to the amount of detail included. For example. If I were to include table names and file layouts it would take more time then just having a requirement that states "we need/will transmit customer transactions". Either way the project goals don't change but the time to complete the requirements phase will be different.

-Tony
hkmartin
...
written by Holly Martin, September 08, 2009
While this makes sense I think you need to have a team that is pretty consisent with how they deliver projects. Perhaps in the consulting business this is more predictable, I wouldn't know. We've looked at some metrics within our department and requirements phase can take anywhere from 0 - 20% of project time. That's a huge range in my opinion, and not something from which we can start benchmarking. SOme of that is based on skill set of the person doing the requirements (junior people tend to take longer than more experience folks, and developer-led projects don't spend any time in requirements). It also depends on how focused the person is who's doing the requirements gathering. I've noticed that when a person is stretched too thin across projects the requirement phase either take longer (because they had to keep jumping back into and out of the project) or the requirements were not detailed enough (lots of rework ended up occuring during design & development due to missed requirements).

I also look a lot at the skill set of my development team. If they need lots of things spelled out, then I'll spend more time in requirement phase to make sure they know what to do in development. If I have a skills tech lead/architect working with me and i can trust them to take the initiative on filling in the gaps, then I may not go as in depth in the requirements (I'll leave it up to developers to flush details out in design).

So in theory I think your estimation method makes sense, I just think you need a pretty consistent project team to make it work.